The U.S. electric car maker Tesla has been cleared after a court decision trees for the planned factory in Berlin – accompanied by new protests. Two Environmentalists climbed on Friday on the trees in the forest in green Heath. The police caught according to information provided by a speaker with the help of altitude rescuers from six to eight metres in height. The action dragged on but, therefore, the detonation of three bombs from the Second world war, had to be postponed by almost three hours.

The two women at the age of 19 and 22 years of age belong to the environmental group “Tree pirates”. It should be according to the police, the same who had already climbed on Monday on the trees. The police have taken a complaint for Trespassing. A spokesman for the environmental group said the Protest against the destruction of the forest and against capitalism in General.

Tesla wants to 90 hectares of forest cleared

On Thursday, was rejected by the higher administrative court of Berlin-Brandenburg, the Urgency of two environmental groups against the premature approval of the grubbing up on Thursday evening in the second instance (OVG 11 S 8.20). So that Tesla can cases, even before the beginning of the vegetation period of the trees on part of the site – it goes first of all about 90 hectares. The decision is not subject to appeal.

facilitate in Potsdam

Brandenburg’s Minister of Economics Jörg Steinbach (SPD) welcomed the court’s judgment in the “image”newspaper: “We accept the verdict with great relief to both of us.” Brandenburg’s Prime Minister Dietmar Woidke (SPD) provides for the U.S. Electric carmaker, with its planned factory in Grünheide, near Berlin, in his self-determined time schedule. Probably in the next week, the grubbing-up can be completed, said Woidke. “I’m very, very glad,” he said more to the decision of the higher administrative court of Berlin-Brandenburg.

“a Free ride for cars of the future instead of sticking rigidly to Principles to Pine plantations,”

The Deputy SPD Chairman, Klara Geywitz wrote on Twitter: “Good news for Tesla and the state of Brandenburg. Free travel for cars of the future instead of sticking rigidly to Principles to Pine plantations.“ The Deputy chief Executive of the Federal Association of German industry (BDI) – Holger Lösch, said the ruling was “an important Signal for the investment location of Germany as a whole”. For the industry in East Germany, the car factory is a “huge opportunity” to grow along with the settlements of other companies manufacturing networks and the Region prosper leave.

Reserved for the Federation for environment and nature conservation Germany (BUND), responded: “We welcome the fact that with the Gigafactory, a car factory is fossil fuel age & the traditional car industry is under pressure,” said the Association on Twitter. “We will continue to critically review whether Tesla contributes in turn to the Success of a real Traffic.”

The Green League also expressed disappointment. Lawyer Dirk Teßmer said: “We were optimistic that it turns out differently.” Of the Association after a dispute is expected before a change at the top. The Association of chief Heinz Herwig Mascher said: “We need to make a restart.” Members had called for the grubbing-up stop for the resignation of the top management. Tesla 830,50 EUR -2,80 (-0,34%) Tradegate

  • 1 day
  • 6 months

course data

approval for the construction of the factory is still out

The Brandenburg state environmental Agency was the early beginning of the trees felling, approved, the complete permit for the construction of the factory is. The environmental organization Green League of Brandenburg and the Association for the preservation of the landscape and protection of species in Bavaria had to stop grubbing on the site. Both had warned that a fait accompli will be created. The administrative court of Frankfurt (Oder) dismissed the Urgency of both associations, however, the past week. The Green League lodged a complaint. The OVG prohibited the further clearing then said for the time being.

Tesla can

Work is now continuing, The court explained in its reasoning to the other tree cases, the statutory requirements for the early start of the construction of the plant had been answered in the affirmative to the right. The competent authority did not have to wait for the expiry of the deadline for objections in the context of public participation until March, because they have the necessary knowledge, in order to assess whether the project is expected to be approved.

“There will be further Attempts to stop Tesla”

the President of The German Institute for economic research, Marcel Fratzscher, predicted after the verdict: “There will be further Attempts to stop Tesla. In this country there is a mentality of preservation of the status quo, which argues against large-scale projects, against changes. The problems lie much deeper. This conflict of interests is now held on the back of Tesla. The damage for Germany in the long term,” said Fratzscher of the editors ‘ network Germany (RND).

There are “a great legal uncertainty for companies,” says Fratzscher. “The German regulations are not so comprehensive, complex, and often ambiguous, that investors know what is true for you.” The Problem for investors is the lack of predictability, so Fratzscher is: “If you don’t know whether the new factory in one and a half years, as Tesla is planning it now, or whether you need five years, then high risks for companies, which often lead to German businesses prefer to invest abroad.”

Economist: the Tesla factory is an incentive for German car manufacturers.

The Tesla-settlement in Brandenburg see Fratzscher as “advantageous for the German car industry”: “German industry was always at its best when you had to assert itself against international competition. If Tesla produced in Brandenburg, Germany, holds the German automotive companies, every day the mirror: See something, what you can’t yet. Make an effort and is catching up!“

press voices to the Protest against Tesla

The newspaper New commented on the verdict against the Green League: “there are quite a lot of things, not to speak out against Tesla: the fact that these cars are the appropriate solution to the environmental and traffic problems that the promised number of Jobs seems to be much too high, that dear old industry should broke be reactivated to seal new surfaces. Of the back of the Green League in the focus. Now you need to brush up on your previously impeccable Image.”

The “Badische Zeitung” wrote: “In this debate, the Eco’s activism, sometimes too far. In his view, self-wind turbines destroy nature, humanity is threatened with extinction and Tesla consumes so much water that Berlin is dying of thirst. You can recommend this to people only to disarm. To not threaten to have achieved democratic progress. Because of the economic associations, and citizen participation in the planning process restrict. Who skin on the drum, and the absoluteness can fall to claim on your feet.”

Tesla wants to build in grünheide, near Berlin, from next year, around 500,000 electric vehicles a year. Due to the commencement of the period of vegetation, the grubbing-up should be completed on the site until the end of February – this is also still possible time. The terrain on which the forest is designated as a business area. In the FOCUS Online In a Lot of rain and hurricane-danger: Here it is on the weekend really stormy FOCUS Online a Lot of rain and hurricane-danger: Here it is on the weekend really stormy