Until Tuesday, the objections to the court are now possible. The state government looks forward to the judge’s decision left. Tesla did not comment on this so far.
Brandenburg government spokesman Florian Engels said on Sunday on request: “We await calmly the decision of the court.” The state office for the environment have the opportunity to take until Tuesday at noon position. “The is made, of course,” he added. “We then put on a short-term decision of the OVG”, wrote Minister of Economics, Jörg Steinbach (SPD) on Twitter.
“Put Germany as an industrial location is not lame”
The Green should speak out clearly for the construction of the Tesla factory in green Heath, and their “roaring Silence break,” demanded the Deputy head of the FDP parliamentary group, Michael Theurer. “Who is for electric mobility, must not hide the construction of a Tesla factory and has to take a stand.” That would be an important Signal to all of the supporters of the Greens, to prevent a wave of lawsuits. Further, Theurer told the “Handelsblatt”: “I appeal to all who are thinking about a lawsuit to go again in. You set Germany as an industrial location is not lame. Exaggerated action madness leads in an economic and ecological impasse.”
the Chairman of The Green League, Brandenburg, Heinz Herwig Mascher, insured on request: “We don’t want to stop Tesla.” However, the company should not be treated differently than others. As long as the procedure had not been completed, is expected to be established any facts that are then reversed.
to prevent The Green League had previously failed with the Association for the preservation of the landscape and protection of species Bavaria, the administrative court of Frankfurt (Oder), with Eilanträgen the tree felling. The court reasoned, in turn, in the second instance, he had to stop so that the advanced clearing work make the provisional prohibition of the removal of trees is required. In addition, should not be assumed, “that the application of the Green League from the outset was obviously futile”.
Receives Tesla no planning permission, the group of forest afforestation
On Thursday, the state environmental Agency of the approval for the premature start of the grubbing-up was granted For the construction of the Tesla plant, but there is still no approval, the process is still running. The approval should not be granted for the project, but should Tesla afforestation, according to the Potsdam Ministry of the environment of the forest appropriately.
The future of the factory site was provided some 20 years ago for the construction of a plant of BMW. Since then it lay fallow, and plant-like animals conquered the new habitat. Tesla has announced against this Background, already environmental protection measures. Tesla 738,10 EUR -3,30 (-0,45%) Tradegate
- 1 day
- 6 months
To the rate of data
In the approval process until 5. March, objections possible. 18. March will be discussed in public. Only after a subsequent examination, there is a approval. The purchase contract is already signed, but flowed still no money. So far, a total of 41 million euros was recognized for the overall 300-acre site. Whether the price was calculated correctly, should be clarified by an independent expert opinion is to be expected with the start of the week is.
Tesla wants. in the first start-up of 92 hectares of forest cleared
Still from Thursday evening to Saturday evening had fallen on the terrain trees like matchsticks: 29 so-called Harvester, and 9 special machines were made in rapid speed, mostly pine trees and for the removal prepared Jörg Carstensen/dpa
it is Planned to clear in the first attempt until the end of February, almost 92 hectares of forest land in grünheide (Oder-Spree). The Rest should be cut down, when the breeding season is in the fall over. From July 2021, Tesla will start the production of 500,000 vehicles per year by the tape run.